Trial dredging schedule
Trial dredging is limited to a period of nine weeks and is
scheduled to begin in early August. It will take place in both the
south and north of Port Phillip Bay as well as a small section at
the entrance to the bay.
Winter presents the most favourable conditions for working at the
entrance to Port Phillip Bay and it is also outside peak tourist
times.
A summary of the proposed schedule appears
below and a map showing the trial dredging locations may
be viewed.
| South Channel East |
5 August |
3 |
| Port Melbourne Channel |
8 August |
3 |
| Entrance to Port Phillip Bay |
11 August |
21 |
| South Channel East |
2 September |
14 |
| South Channel West |
16 September |
4 |
| Port Melbourne Channel |
21 September |
14 | Please
note that these dates are subject to weather conditions and other
considerations and are only to be used as a guide. Please see
applicable Notices to mariners for more information.